Camp Smith Construction Updates
Monday, January 25, 2010
All 10 homes are in various stages of vertical construction at this time. Roofing shingles on Pads 1 through 6 are almost complete.
Electrical and plumbing rough-in is complete on Pads 1 through 6 and drywall has started on Pads 1 through 6.
Roof sheathing is complete on Pads 7 through 10. Electrical and plumbing rough-in is complete on Pads 9 and 10.
The slopes have been stabilized and the grass is growing in nicely.